Institutional Project: Collinte - 911 Dispatch

Back to All Projects
  • Project Name: COLLINTE - 911 Dispatch
  • Project Address: 5700 Yonge St, North York, ON M2N 5M9
  • Project Start Date: December 27, 2023
  • Project Completed Date: April 17, 2024
  • Project Value at Completion: $21,799.70
  • Consultant: E-Lumen International Consulting

Key Components

  • 1. Initial Assessment and Planning:

    • Custm Electric conducted an initial assessment of the existing cooling unit and the data room's electrical setup.
    • Custm reviewed the specifications and requirements for the replacement cooling unit to ensure compatibility and functionality.
  • 2. Temporary Power Setup:

    • Before disconnecting the existing cooling unit, Custm Electric set up temporary power for the backup cooling units.
    • This ensured continuous cooling during the transition period, crucial for maintaining the operational integrity of the dispatch data room.
  • 3. Disconnecting the Existing Cooling Unit:

    • Custm Electric safely disconnected the power supply to the existing cooling unit.
    • Custm ensured proper shutdown procedures to prevent any disruptions or damage to the data room’s sensitive equipment.
  • 4. Providing New Services for Replacement Cooling Unit:

    • Custm Electric installed new electrical services required for the replacement cooling unit.
    • This involved running new wiring, connecting electrical panels or subpanels as needed, and ensuring proper grounding and safety measures.
  • 5. Integration and Testing:

    • Once the new services were in place, Custm Electric integrated the replacement cooling unit into the data room’s electrical system.
    • Custm conducted thorough testing to verify the functionality and efficiency of the new cooling unit.
    • Testing included ensuring proper temperature control, adequate airflow, and energy efficiency.
  • 6. Final Configuration and Cleanup:

    • Custm Electric finalized the configuration of the electrical connections for the replacement cooling unit.
    • Custm tidied up the work area, removing any debris and ensuring the data room was left clean and organized.
  • 7. Documentation and Handover:

    • Custm Electric prepared documentation including as-built drawings, specifications of installed equipment, and any necessary operating instructions.
    • Custm provided training or instructions to the data room staff on operating and

    maintaining the new cooling unit.

  • 8. Post-Installation Support:

    • Custm Electric offered post-installation support, including troubleshooting and addressing any issues that arose after installation.
    • Custm remained available for follow-up inspections or adjustments as required by the client.

Throughout the project, Custm Electric maintained clear communication with the 911

paramedic dispatch center staff to ensure minimal disruption to their operations.

CUSTM's expertise in handling both temporary and permanent electrical setups ensured a smooth transition to the new cooling unit, crucial for maintaining the reliability and functionality of the dispatch data room's operations.

Recent Post

Public library, lighting and power systems upgrade
September 24, 2024
Electrical work for a large-scale public library, including lighting and power systems.
A large warehouse filled with lots of boxes and pallets.
September 24, 2024
CUSTM Electrical was chosen to install the specialized electrical systems for Ground Effects’ paint booths. Their state-of-the-art facility demands precise, efficient, and safe electrical solutions to ensure optimal performance and compliance.
Industrial: Brunswick Brewery Renovation
September 23, 2024
Electrical work for a leading brewery, including process automation and lighting.
Fire Station 102 Expansion and Renovation
September 23, 2024
Electrical installations supporting critical public safety infrastructure.
COTA Health Renovation
September 23, 2024
Cota Health facility is designed to create a comprehensive environment for mental health and wellness services.
Share by: